Continuing our twelve day countdown to Christmas, today’s blog is a nice juicy case study! However, this isn’t just any case study, this case study features blocked culverts, four foot long tree roots, over 50 TONNES of silt, and of course, an expert team of Hydro Cleansing engineers getting the job done. 

Back in the Summer we were called out to deal with some blocked culverts, syphons and silt traps by the NPL. On our arrival it was clear that there was something seriously big blocking the syphon under the railway, even our camera couldn’t travel underneath to get a clear picture. Upon further investigation the engineers discovered that the blockage was clusters of tree roots growing through the tunnels. Check out the full scope of works below!

blocked culvert case study christmas

Client – National Physical Laboratories | Kings River Outfall Desilting

Scope of Works – Desilting of culvert | Root cutting in syphon under railway | Desilting of silt traps

  1. The culvert in Normansfield Road had a high level of silt and elevated water level, the camera was then unable to return a picture of the internal condition of the pipe. We needed to remove this silt and reduce the flow during the survey, we then proposed to undertake this with a super combination unit taking one day to complete and resurvey.
  1. The syphon under the rail way had root ingress which prevented the passage of the camera, to remove this we needed to reduce the flow through the culvert and use high pressure root cutting with specialist root cutting nozzles suitable for large bore pipes. We took one day to complete and resurvey.
  1. The silt traps in five manholes needed de-silting, they contained an average of 1m of silt each. The silt traps are 2.5m in diameter which will yield approximately nine tonnes each. We took two days to complete.

case study blocked culvert and camera christmas

case study blocked culvert and roots christmas

Check out those roots! Job done!